Timeline

How Long Does Custom Software Development Take?

Most custom software projects: 10-16 weeks. Simple MVPs: 6-8 weeks. Complex enterprise: 4-9 months. This guide breaks down each phase, what affects duration, and how to speed things up (or when you shouldn't).

Article illustration

Table of Contents

Typical Timeline by Phase

Discovery: 2 weeks — Requirements, technical audit, scope definition, fixed-price quote.

Design: 2 weeks — UX/UI, architecture, API specs. You sign off before we code.

Development: 6-12 weeks — Agile sprints, weekly demos. Most variable. Simple: 6 weeks. Complex: 12+.

Delivery: 1-2 weeks — Deploy, train, document, handoff.

Total: 10-16 weeks for a typical project. See our process guide for detail on each phase.

Concept diagram

Timeline by Project Type

Simple MVP: 6-8 weeks. One core workflow, auth, basic payment. Minimal integrations.

Internal tool / operations platform: 10-14 weeks. Multiple workflows, integrations, reporting.

SaaS product: 12-16 weeks. Billing, team features, admin, polish.

Enterprise system: 4-9 months. Complex integrations, compliance, scale. Phased delivery.

What Affects Duration

  • Scope — More features = more time. Stick to must-haves for phase 1.
  • Integrations — Each integration adds 1-3 weeks. Legacy systems with poor APIs add more.
  • Your availability — Delays in feedback, sign-off, or access to systems push the timeline.
  • Complexity of logic — Simple CRUD vs. complex workflows, approvals, calculations.
  • Design requirements — Custom design takes longer than UI library. Brand-heavy = more time.

Can We Go Faster?

Yes, within limits. Add developers to parallelize work — but some tasks don't parallelize (architecture, integrations). Reduce scope: cut phase 1 to the absolute minimum. Use a UI library instead of custom design. Be available for fast feedback. We can often compress 16 weeks to 12 with tight scope and good collaboration. Going from 12 to 6 weeks usually means cutting scope significantly.

Frequently Asked Questions

When does the clock start?

At kickoff — when we have access to requirements, systems, and stakeholders. Delays in onboarding (e.g., waiting for API access) push the start.

What if we need it in 4 weeks?

Scope down aggressively. Or use no-code (Airtable, Retool) for a v1. True custom in 4 weeks is only possible for very small scope — e.g., a single workflow, no integrations.

Get a Timeline for Your Project

We'll give you a realistic timeline after Discovery.